Overview

The development consists of a new five storey clinical building with enclosed roof top plant to the southern side of the complex consisting of approximately one third of the total site area together with a five storey atrium linking existing blocks to the east and west and the formation of a new vehicular entrance. The Construction programme was divided into two phases being the construction of the new Acute Wing followed by refurbishment and fit out of certain decanted areas following completion of phase 1

  • Client:
  • NHS
  • Contract Type:
  • Traditional JCT
  • Architect:
  • Billy Gardner
  • Sector:
  • Healthcare